What is the operating procedure of the pe hot melt hydraulic butt welder?
May 03, 2018

What is the operating procedure of the pe hot melt hydraulic butt welder?

There are seven steps for fixing, centering, heating and welding.

The first step: preparation

The pe pipe hot-melt butt welder is ready, including the hydraulic station, milling cutter, heating plate and other related power supply, and the docking frame is placed in a stable manner;

Step 2: Place

Two sections of pe tubes that need to be welded are placed in the docking frame, and the connection is disposed in the middle of the four jigs of the docking rack.

The third step: fixed

Close the upper and lower brackets of the docking frame and fix the PE pipe with bolts.

Step 4: Milling

Take the milling cutter out of the basket and place it in the middle of the two pe tubes. Push the lever of the hydraulic station and contact the two pe tubes with the milling cutter until the two connecting planes are milled and the continuous strips of debris are milled.

Step 5: Centering

Because the fixed pipe may be offset during the milling process, it must be centered again to adjust the amount of misalignment. Of course, it must be careful not to contaminate the port, otherwise it must be milled again.

Step 6: Heating

Place the milling cutter back into the basket, remove the hot plate from the basket and place it in the middle of the two pe tubes, and heat them. After the two tubes have started to turn over and meet the requirements, return the heating plate.

Step 7: Welding

Immediately after removing the hot plate, press the required pressure and quickly close the PE port to be welded.